Table 7 Structural works from 2011 to 2015.

From: Sustainability, institutional arrangement and challenges of community based climate smart practices in northwest Ethiopia

Type of structure Five year plan Achievement %
Crop land terracing (km) 377,061 368,062 97.6
Hillside Terracing (km) 85,207 53,744 63.1
Check dam (km) 10,776 6748 62.6